Street Reconstruction

  • The City is rebuilding Gresham's residential streets that are listed in failed condition. 

  • Construction is complete

    Crews are done with paving work. This multi-year project is complete.  

    • Project Background
    • 2023 Streets
    • Construction Impacts
    Project Background

    Hitting the Streets: Rebuilding Gresham’s streets

    The City is reconstructing its most deteriorated residential streets in the largest street investment in Gresham’s history. This was a multi-year project, completed fall 2023.  

    Street selection

    • Local streets were evaluated using a pavement condition rating.
    • All streets rated below 25 out of 100 are included in this project. 
    • The City is addressing the worst of the worst streets.
    • Preventative maintenance work will continue to extend the life of streets. 

    Types of work 

    • Sidewalk ramp improvements for pedestrian safety at intersections.
    • Street reconstruction.

     Timeline

    • March - June: Sidewalk ramp work followed by street reconstruction.  
    • June - October: Street reconstruction work.

    Scheduling

    Roadwork schedules are subject to change. Check the Street Reconstruction Map for more information.

    • Rain will delay street repaving work.
    • Unexpected issues with equipment, supplies or utility lines could extend the project. 

    Contact

    Environmental Services, 503-618-2525

      Additional information

      2023 Streets

      Streets paved in 2023, by neighborhood 

      Northwest  

      • NW Division Street: NW Eastman Parkway to NW Wallula Avenue

      Central City  

      • NE 5th Street: NE Kelly Avenue to NE Cleveland Avenue  
      • NW 15th Street: Parking lot to NW Main Avenue  
      • SW 4th Street: SW Florence Avenue to SW Walters Road  

      Gresham Butte 

      • SW 7th Street: 1098 SW 7th Street to SW 4th Street 

      Hollybrook 

      • SW 7th Street: SW 4th Street to SW Eastman Avenue 

      North Central 

      • N Maine Avenue: NW 20th Street to NW 22nd Street 
      • NE 16th Court: End to NE Juniper Avenue 
      • NE 18th Court: End to NE Juniper Avenue 
      • NE 18th Street: NE Juniper Court to NE Cleveland Avenue 
      • NE 19th Street: N Main Avenue to NE Juniper Court 
      • NE 20th Drive: NE Hood Court to be 19th Street 
      • NE 22nd Court: End to NE Cleveland Avenue
      • NE 22nd Court: NE 23rd Street to end 
      • NE 22nd Street: NE Cleveland Avenue to NE Morlan Avenue 
      • NE 23rd Place: NE Hood Avenue to NE Kelly Avenue 
      • NE 23rd Street: 55 NE 23rd Street to NE Hood Avenue 
      • NE 24th Street: NE Spruce Avenue to NE Cleveland Avenue 
      • NE 25th Street: NE Beech Avenue to NE Linden Avenue 
      • NE 25th Street: NE Cleveland Avenue to NE Maple Avenue 
      • NE 25th Street: NE Juniper Avenue to NE Spruce Avenue 
      • NE 26th Street: 157 west of NE Linden Ave to NE Linden Avenue 
      • NE 26th Street: NE Morlan Avenue to NE Maple Avenue 
      • NE 27th Street: NE Morlan Avenue to NE Liberty Avenue 
      • NE 28th Court: NE Evelyn Avenue to end 
      • NE 29th Street: NE Evelyn Avenue to NE Liberty Avenue 
      • NE 30th Court: NE Liberty Avenue to end 
      • NE 30th Drive: 521 NE 30th Drive to NE Elliott Avenue 
      • NE 30th Lane: End to NE Liberty Avenue 
      • NE 33rd Street: NE View Avenue to dead end 
      • NE 34th Street: NE Francis Avenue to city limits @ #2106 NE 34th Street 
      • NE 35th Street: NE View Avenue to NE Francis Avenue 
      • NE 36th Court: NE Hogan Drive to end 
      • NE Beech Avenue: NE 18th Street to NE 19th Street 
      • NE Beech Avenue: NE 24th Street to PC @ #2554 NE Beech Avenue 
      • NE Beech Court: NE 22nd Street to end 
      • NE Elliott Avenue: NE 22nd Street to NE 24th Street 
      • NE Elliott Avenue: 2807 NE Elliott Avenue to NE 30th Drive 
      • NE Elliott Place: NE 18th Street to end 
      • NE Evelyn Avenue: NE 27th Street to NE 29th Street 
      • NE Francis Avenue: NE 33rd Avenue to NE 35th Avenue 
      • NE Glisan Street: 23535 NE Glisan Boulevard to NE 242nd Drive 
      • NE Glisan Street: 223rd Avenue to 23535 NE Glisan Boulevard 
      • NE Hood Avenue: NE 20th Drive to NE 22nd Street 
      • NE Hood Avenue: NE 22nd Street to NE 24th Street 
      • NE Hood Court: NE 19th Street to NE 20th Drive 
      • NE Juniper Avenue: Dead end to NE 18th Street 
      • NE Juniper Avenue: NE 24th Street to NE 25th Street 
      • NE Juniper Court: NE 19th Street to end 
      • NE Kelly Avenue: NE 22nd Street to NE 23rd Place 
      • NE Liberty Avenue: NE 25th Street to 105’s of 25th Street 
      • NE Liberty Avenue: NE 26th Street to SE Stark Street 
      • NE Linden Avenue: NE 25th Street to NE 26th Street 
      • NE Linden Avenue: NE 26th Street to NE Elliott Avenue 
      • NE Linden Place: End to NE 25th Street 
      • NE Maple Avenue: NE 25th Street to NE 27th Terrace 
      • NE Morlan Avenue: NE 22nd Street to 2283 NE Morlan Avenue 
      • NE Morlan Avenue: NE 25th Street to NE 27th Street 
      • NE Roberts Avenue: NE 19th Street to NE 22nd Street 
      • NE Roberts Court: NE Roberts Avenue to end 
      • NE Spruce Avenue: NE 23rd Street to NE 25th Street 
      • NW 23rd Street: NW Salmon Drive to 55 NE 23rd Street 
      • NW Earl Court: NW 20th Street to end 
      • NW Miller Avenue: NW 20th Street to NW 23rd Street 
      • SE 205th Avenue: SE 207th Avenue to SE Stark Street 
      • SE 205th Drive: SE Main Drive to SE 207th Avenue 
      • SE 209th Avenue: NW Burnside Road to SE Morrison Street 
      • SE 210th Avenue: SE Salmon Street to SE Morrison Street 
      • SE Main Drive: SE 205th Drive to SE 209th Avenue 
      • SE Morrison Street: SE 209th Avenue to SE 212th Avenue 
      • SE Yamhill Street: SE 210th Avenue to SE 212th Avenue 

      North Gresham  

      • NE 196th Avenue: NE Holladay Street to NE Halsey Street 
      • Northeast 
      • NE 19th Street: NE Hogan Drive to NE Hogan Road 
      • NE 19th Street: NE Hogan Road to Royal Greens Apartments Gate 
      • NE Country Club Court: End to NE 23rd Street 
      • NE Francis Court: End to NE 23rd Street  
      • NE View Avenue: NE 33rd Avenue to NE 36th Court  
      • NE View Court: End to NE 23rd Street  

      Rockwood 

      • SE 185th Avenue: SE Stark Street to E Burnside Street  
      • SE Oak Street: End to SE 185th Avenue  
      • SE Pine Street: SE 181st Avenue to SE 185th Avenue 
      Construction Impacts

      Prepare for paving 

      Curbside trees, shrubs and plants need to be trimmed prior to paving. 

      Tree and shrub requirements  

      1. Do not block street or traffic signs and signals. 
      2. Overhanging tree branches need to be 12 feet above the street and 8 feet above the sidewalk. 
      3. Shrubs and plants should not extend beyond the curb or sidewalk. 

      What to expect during construction 

      The contractor, City project team and inspectors will be on site. We will make every effort to minimize impacts.

      • Work hours are 7:00 am – 7:00 pm for neighborhood streets. 
      • The contractor will leave a 24-hour notice on your door before work begins. The street must be clear of vehicles or other materials. 
      • Watch for no parking signs. Vehicles may be towed at the owner's expense if left on the street at the time of paving.  
      • Mail and package delivery will continue during construction 
      • Garbage haulers will be notified.
      • Prior to construction, locate crews may mark the street to indicate the location of underground utilities.  
      • Weather can impact schedules. 

        Construction steps

        1. Remove existing sidewalk curb materials, install sloped ramps to provide improved safety at pedestrian crossings.
        2. Street reconstruction preparation. Construction equipment and materials will be parked on the street.  Project street signs will be posted.
        3. Existing pavement will be ground and removed with large milling machines.
        4. Street shaping, grading and compaction will occur. 
        5. Paving (If it is raining, paving will be delayed). Asphalt is applied and then rolled smooth.  
        6. On larger streets there will be signal detection, crosswalks, bike lanes and long line striping re-installed. 

        Construction impacts

        Sidewalk ramp work
        • Temporary sidewalk and bike lane closures; possible flaggers directing traffic; and limited on-street parking.
         Street reconstruction
        • Limited on-street parking. 
        • Dust is likely. 
        • Temporary loose gravel on the street.   
        • Temporary vibration could be felt inside homes.
        • Reduced speeds.
        • Partial street closures, resulting in delays.
        • Access to your driveway may be limited. 

        Contacts

        • If your vehicle is towed, contact Police Records at 503-618-2318
        • For all other questions, contact the Department of Environmental Services at 503-618-2525
        • Residential paving
        • Hitting The Streets Before and After closeup
        • Hitting the Streets- 182nd

        1 of 4
        • When possible, paving crews are resurfacing one half of the street at a time to provide local access during construction.

        • The street improvements are quite noticeable. 

        • Crews were able to resurface SE 182nd from SE Division Street to SW 5th Drive in five days.